V1

Tabba II
Ringo Contract: WO-11318
41%
Completion
Current: Assembly

๐Ÿ› ๏ธ 7-Stage Progress Timeline

1

Material Ready

Done
Started: 2026-06-05 12:00 ยท Completed: 2026-06-06 12:00
Sub-steps (4/4 done)
  • โœ“ 1. BOM verification
  • โœ“ 2. Parts kitting inspection
  • โœ“ 3. Outbound handover to workshop
  • โœ“ 4. Critical items recheck (seals)
2

Sandblasting

Done
Started: 2026-06-06 12:00 ยท Completed: 2026-06-08 12:00
Sub-steps (3/3 done)
  • โœ“ 1. Arrival at subcontractor
  • โœ“ 2. Sealing face protection / Sandblasting / Inspection
  • โœ“ 3. Transport back to SCC
3

Pre-assembly

Done
Started: 2026-06-12 10:02 ยท Completed: 2026-06-12 10:02
Sub-steps (5/5 done)
  • โœ“ 1. Dismounting of bush stem of AUMA
  • โœ“ 2. Bush stem machining
  • โœ“ 3. Bush stem testing
  • โœ“ 4. Remounting bush stem of AUMA actuator
  • โœ“ 5. Screws testing between bonnet & glad
4

Assembly

In progress
Started: 2026-06-08 12:00
Sub-steps (4/12 done, 1 doing)
  • โœ“ 1. Position valve body in pit fixture
  • โœ“ 2. Install disc
  • โœ“ 3. Stem & bonnet prepared โ€” Screws of bonnet & gland were repaired.
  • โœ“ 4. Install bonnet, stem
  • โ— 5. Install seals & packing โ€” took 4 hours tightening the body gasket
  • โ—‹ 6. Pre-tighten gland bolts
  • โ—‹ 7. Body nut hydraulic tightening (2 stages)
  • โ—‹ 8. Final gland bolt tightening
  • โ—‹ 9. Lift out from pit
  • โ—‹ 10. AUMA actuator coupling & alignment
  • โ—‹ 11. AUMA actuator power connected
  • โ—‹ 12. AUMA actuator calibration
5

Testing & FAT

Pending
Sub-steps (0/7 done)
  • โ—‹ 1. Horizontal adjustment
  • โ—‹ 2. Clamp onto test bench
  • โ—‹ 3. Shell hydrostatic test
  • โ—‹ 4. Backseat test
  • โ—‹ 5. Seat leakage test
  • โ—‹ 6. Test report
  • โ—‹ 7. Download from test bench
6

Painting

Pending
Sub-steps (0/5 done)
  • โ—‹ 1. Protection & surface cleaning
  • โ—‹ 2. Primer coating
  • โ—‹ 3. Intermediate / Topcoat
  • โ—‹ 4. Coating thickness inspection
  • โ—‹ 5. Drying & curing
7

Packing

Pending
Sub-steps (0/4 done)
  • โ—‹ 1. Protection
  • โ—‹ 2. Custom wooden crate & cushioning
  • โ—‹ 3. Crating, fixing & lashing
  • โ—‹ 4. Packing list & shipping documents
8

Shipped

Pending
Sub-steps (0/3 done)
  • โ—‹ 1. Loading
  • โ—‹ 2. Bill of lading / Logistics documents
  • โ—‹ 3. Customer receipt confirmation

๐Ÿ“ธ Photo Records (9)

Assembly
Removing air conditioning ducts
2026-06-12 19:08
Assembly
2026-06-12 16:41
Assembly
2026-06-12 11:25
Assembly
2026-06-12 11:25
Assembly
2026-06-12 10:01
Assembly
2026-06-12 10:01
Assembly
2026-06-11 18:20
Assembly
2026-06-11 18:20
Assembly
2026-06-11 18:20