📊 Overall Project Progress in SCC Factory
Saudi Arabia · Tabba II & Qassim II · 6× 24" 2500# Check Valves
📄 Ringo Contract: WO-11318
🇸🇦 Tabba II: V1 / V3 / V4
🇸🇦 Qassim II: V2 / V5 / V6
8%
Overall completion (factory only)
Not Started
4
Sandblast
0
Pre-asm
1
Assembly
1
Test/FAT
0
Painting
0
Packing
0
Shipped (out)
0
📈 Gantt Chart: Plan vs Actual
Project span: 2026-06-01 → 2026-08-02 (9 weeks) · Stage 7 Shipped excluded
Planned
Actual (done)
Actual (in progress)
Today (2026-06-12)
Valve
W23
6/1
W24
6/8
W25
6/15
W26
6/22
W27
6/29
W28
7/6
W29
7/13
W30
7/20
W31
7/27
V1
Plan
Actual
V2
Plan
Actual
V3
Plan
Actual
V4
Plan
Actual
V5
Plan
Actual
V6
Plan
Actual
V1
Plan: 2026-06-06 → 2026-07-05 (29d)
Actual:
2026-06-05 → ongoing
V2
Plan: 2026-06-14 → 2026-07-13 (29d)
Actual:
2026-06-12 → ongoing
V3
Plan: 2026-06-22 → 2026-07-18 (26d)
Actual:
Not started
V4
Plan: 2026-07-06 → 2026-08-01 (26d)
Actual:
Not started
V5
Plan: 2026-06-24 → 2026-07-20 (26d)
Actual:
Not started
V6
Plan: 2026-07-06 → 2026-08-01 (26d)
Actual:
Not started
V1
Tabba
Assembly
41%
1
Ready
2
Sandblast
3
Pre-asm
4
Assembly
5
Test/FAT
6
Painting
7
Packing
8
Shipped
📸 Latest photo
V2
Qassim
Pre-assembly
6%
1
Ready
2
Sandblast
3
Pre-asm
4
Assembly
5
Test/FAT
6
Painting
7
Packing
8
Shipped
📸 Latest photo
V3
Tabba
Material Ready
0%
1
Ready
2
Sandblast
3
Pre-asm
4
Assembly
5
Test/FAT
6
Painting
7
Packing
8
Shipped
V4
Tabba
Material Ready
0%
1
Ready
2
Sandblast
3
Pre-asm
4
Assembly
5
Test/FAT
6
Painting
7
Packing
8
Shipped
V5
Qassim
Material Ready
0%
1
Ready
2
Sandblast
3
Pre-asm
4
Assembly
5
Test/FAT
6
Painting
7
Packing
8
Shipped
V6
Qassim
Material Ready
0%
1
Ready
2
Sandblast
3
Pre-asm
4
Assembly
5
Test/FAT
6
Painting
7
Packing
8
Shipped
📅 Today's Activity (2026-06-12)
V1, bonnet & stem installed, body gasket, cover, retainer ring installed, bonnet sujection plate installed.
🔧 In progress
V1
Stage updated
16:41
✅ Done
V1
Stage updated
10:02
🔧 In progress
V2
Stage updated
06:04
📸 New Photos Today (8)